Setting out of Gridlines On Site
Today I
wish to further discuss on setting out gridlines in a construction site.
Before and
construction can be done, a set of construction drawings would be issued by the
Consulting Architect firm. In these drawings the site layout plan and floor
plans will be found. In these plans, there will be Grid Lines indicated with
dimensions given. The grid lines allow references to be made in terms of
position/location of various elements in the project. For example a partition
wall position is determine in the floor plan by having dimensions indicated in
the x and y axis, let say for an example - 2 meters from Gridline A, and 1
meter from Gridline 2
The Main
Contractor will then engaged a license surveyor to set out the grid lines on
site. The License surveyor will purchase a survey plan from the government land
survey department indicating the true coordinate control points near the
construction site and the license surveyor field team will for transfer and
establish new control points if necessary and from these control points will go
about setting out the grid lines in the construction site.
The license
surveyor field team will normally set up the gridline reference points a few meters
away from the building outline. When marking the gridline reference points they
will as far as possible marked it on a permanent structure such as if there is
a concrete pavement or a boundary wall or fence. If that is not possible they
will drive a wooden peg/stake into the ground and marked the grid line
reference point of the top of the wooden peg with a steel nail.
After the
grid line setting out is done on site, they will bring their field data back to
their office and have a drawing made out, showing the gridlines they have
marked on site and the offset distances and other relevant information. When
the gridline setting out drawing is ready, the license surveyor will endorse drawing
and issue it to the main contractor.
Once the
main contractor receives the drawing, he will give this drawing to his Site
Engineer or the in-house surveyor if he has one. The Site Engineer or in-house
surveyor has to then check and verify that the license surveyor markings on the
drawing are similar to the markings on site. Prior to this, the Site Engineer or
In-house surveyor has to protect all the marked points immediately after the license
surveyor field team completed the marking of the gridline points. This is to
avoid the gridline control points from being disturbed by other site activities.
If the site
has a theodilite then the setting up of profile or batter board is not
necessary.
However, if there is no theodilite, then preparation of profile or
batter board [see below figure 1 and 2 picture] for the transfer of the license
surveyor grid lines to the top of the profile board is necessary. This activity
is normally performed by the carpenters for the project. Profile or batter
board is done so that the gridline point’s mark by the license surveyor field
team is transferred up to a nail point on the profile board. The height of the
profile board is normally 500mm to 1000mm above the formation level of the
building. Normally the license surveyor points are either driven wooden pegs on
the ground, or points driven by nails on a pavement or centre punch points on a
brick wall. The purpose of a profile board is when there is no theodilite to give
a line of sight for the gridline; the carpenters can tie a carpenter nylon
string from one gridline point on the profile board to the corresponding gridline
point at the other end of the site.
However,
using profile board for setting out works is not encouraged for the following
reasons:
1) Error in
transferring from surveyors point to profile board.
2) When the
profile board is disturbed
3) Inaccuracy
in transferring from the carpenter string to the work element
4)
Different elevation on one end of profile board to the opposite end.
I realize
my explanation may not be clear on gridline setting up, so I went to YouTube to
search for some videos on site setting up and have attached it in this Post.
However, the videos are also not very clear but it does give one a rough idea.
This end’s
today Post. Have a nice day!
If you would like more information, please contact us or your local dealer. We accept trade-ins of any competitive equipment. Read More
ReplyDeleteThey will be sourced from a local nursery that specialises in growing and training mature trees. Instant screening? No problem!chain link fence gate
ReplyDelete